Quick answer
- A custom startup website of five to ten pages typically takes three to six weeks from the agreed brief to launch. A single landing page takes one to two weeks.
- Websites with an admin dashboard take six to ten weeks, and sites with bookings, members' areas or online payments take two to four months.
- The timescale is set less by the designer than by five things on your side: content, decision-makers, features, branding and the designer's start date.
- Waiting for page text and images is the most common reason a website launches late.
- You can launch sooner by starting with the essential pages, writing the content first and giving one person the final say.
- A website promised in a few days is a template, not a designed website.
- Work backwards from your launch date, add two weeks of contingency and agree the brief by that date.
"How long will it take?" is usually the second question a founder asks us, straight after the price. The honest answer is that it depends on the kind of website and on how quickly decisions and content arrive, but "it depends" is not much use when you are planning a launch. So this guide gives real numbers for each type of website, explains what actually sets the timescale, shows a realistic week-by-week schedule for a typical startup website and sets out how to launch sooner without cutting corners.
The figures are based on how we run startup web design projects at DigitalPod, where the design and the build are done by the same people in-house. Projects that pass between a designer and a separate developer tend to take longer, because every handover adds waiting time.
The Short Answer: Timescales by Type of Website
These assume a custom design, an experienced designer, a clear brief and a client who responds within a couple of days. They run from the brief being agreed to the website going live.
| Type of website | Typical time | What usually stretches it |
|---|---|---|
| Landing page or one-page website | 1 to 2 weeks | Copy not written, no logo yet |
| Startup or small business website, 5 to 10 pages | 3 to 6 weeks | Content arriving late, slow feedback |
| Website with an admin dashboard | 6 to 10 weeks | Undecided content structure, extra features |
| Bookings, members' area or online payments | 2 to 4 months | Third-party integrations, testing, changes of scope |
| Redesign of an existing website | 3 to 8 weeks | Migrating old content, redirects, more pages than expected |
| Logo and website designed together | Add 1 to 2 weeks | Logo decisions taking longer than planned |
A do-it-yourself site on a website builder can be live in a weekend, but most founders who go that way spend several weeks of evenings on it and still end up with something that looks like a template. Our comparison of custom websites and website builders covers that trade-off properly.
Where the Time Actually Goes
In a typical five-week startup project, roughly a third of the time is design, a third is development and testing, and a third is waiting: for content, for feedback on designs, for sign-off on the test site. The waiting is not wasted time, it is the time your decisions take, but it is the part of the schedule that only you control. Our guide to the website design process walks through each stage in turn and how long it takes, so we will not repeat that here. What matters for planning is the next section: the things that make one project take three weeks and an identical one take ten.
The Five Things That Set Your Timeline
1. Whether the content is ready
Page text and images are the number one cause of late launches, and it is not close. A designer can lay out a page around rough draft copy, but the final build, proofreading and testing cannot finish until the real words arrive. If you have not started writing, our guide to writing website copy for a startup gives you a method, and if you would rather not write it yourself we can quote for copywriting alongside the website.
2. How many people have to agree
A founder who can look at a design and decide the same day keeps a project moving. Two co-founders who each want changes, a board that meets fortnightly, or an investor who wants a look before sign-off can each add a week per round of feedback. Agree before the project starts who has the final say, gather everyone's comments into one list and send it once.
3. Features and integrations
A brochure website is a known quantity. Every feature beyond that, such as online booking, a members' area, payments, a customer relationship system that needs connecting, or an admin dashboard so you can edit content yourself, adds design, development and testing time. Features that depend on another company's system add time you cannot control, because you are waiting on their documentation, their approvals or their support. Decide which features genuinely need to be in the first version and which can follow in a second phase.
4. Whether the branding exists
A website is designed around a logo, a colour palette and typography. If those do not exist yet, they have to be created first, which is why we quote logo and brand design alongside the website and schedule it at the start. Arriving with a finished logo and brand colours removes a week or two. Our guide to startup branding explains the minimum a designer needs to begin.
5. The designer's start date
Timescales are quoted from when work begins, and a good studio often has projects queued. Ask when they can start, not just how long the project takes. A three-week build that starts in a month is a seven-week wait. If your date is fixed, say so at the first conversation; a realistic designer will tell you whether it can be done and what they need from you to hit it.
A Realistic Five-Week Schedule
Here is what a typical startup website of around eight pages looks like week by week when it goes well. It assumes the logo exists, the deposit is paid and the content arrives by the end of week two.
- Week 1: discovery and structure. A call about your business, customers and goals. The page structure, a content outline for each page and the design direction are agreed. You start on the page text.
- Week 2: home page design. The home page is designed in full and sent for feedback. You send your comments in one batch, and the final content for the other pages arrives.
- Week 3: remaining pages and build. The inner pages are designed from the agreed direction while the build of the approved home page begins.
- Week 4: build and test site. The whole website is built, the content goes in, forms are connected and the site goes onto a private test server for you to try.
- Week 5: review, fixes and launch. Final text changes and fixes, checks on phones and tablets, analytics and Search Console set up, domain connected, website live.
Every week in that schedule has a point where the project waits on you. Miss the content deadline in week two by a fortnight and the launch moves by a fortnight, even though nothing else changed.
How to Launch Sooner Without Cutting Corners
- Launch with the essential pages. Home, about, your main services and contact are enough to go live. Case studies, extra service pages and a blog can follow. Our guide to what pages a startup website needs helps you draw the line.
- Write the content before the design starts. Even rough drafts let the designer work with real words rather than placeholders.
- Give one person the final say. Collect opinions by all means, but have one decision-maker and one list of feedback per round.
- Sort the branding first. Decide the logo and colours before the website design begins, or have them designed together.
- Choose a designer who builds in-house. When the people who design the site also build it, there is no handover and no second company's schedule to fit around. Our guide to what a website designer does explains why that matters.
- Keep phase two for phase two. Bookings, member areas and dashboards can be added to a well-built site later. If you think you will want them, say so at the start so the foundation allows for it.
What a "Website in a Week" Really Means
Some services promise a finished website in days. What arrives is a template with your logo, colours and text dropped in: no discovery, no design to approve, no structure planned around your customers and very little testing. That can be a reasonable choice for a side project or for testing an idea, but it is a different product from a designed website, and it should be priced like one. If a landing page is genuinely all you need right now, our guide to landing pages versus full websites will help you decide, and a professionally designed single page is a one to two week job rather than a template.
Planning Around a Launch Date
If the website has to be live for a launch event, a funding round, a trade show or the end of a contract with your current provider, work backwards. Take the typical timescale for your type of site from the table above, add two weeks of contingency, and that is the date the brief needs to be agreed and the deposit paid. Allow for the designer's start date on top.
Use the weeks while the site is being built. Register the domain and set up business email, claim your Google Business Profile, write the legal pages, ask early customers for reviews and get your social profiles ready to point at the new site. Our startup website checklist lists all of it, and our guide to getting a startup website found on Google covers what to do in the first weeks after launch.
How We Keep Projects on Schedule
At DigitalPod the same small team designs and builds every website, so there are no handovers to wait for. We agree the page structure and a content plan in the first week, design the home page first so direction is settled early, put every site on a private test server before launch and take a 50% deposit with the balance on completion. Startup website design starts from £2,400 for a site of up to around ten pages, and if you have a date you need to hit, tell us when you get in touch and we will tell you honestly whether it can be done.
Frequently Asked Questions
Can a website be built in two weeks?
A single landing page or a one-page website can, provided the content is ready and decisions are made quickly. A custom website of five to ten pages cannot be properly designed, approved, built and tested in two weeks without skipping the steps that make it work. If you have a hard deadline that close, launch with the essential pages and add the rest in the weeks after.
How long does a website redesign take?
About the same as a new website of the same size, so typically three to eight weeks for a brochure site. The design and build are no quicker, and a redesign adds two jobs a new site does not have: moving the existing content across and setting up redirects from the old page addresses so you keep your Google rankings.
Does designing a logo at the same time add to the timescale?
Typically one to two weeks at the start of the project, because the logo, colours and typography need to be agreed before the website design can be finalised. It still tends to be quicker than running two separate projects with two suppliers, and the website design is better for it because everything is created together.
How long after launch does it take to show up on Google?
Google usually finds and indexes a new site within days of the sitemap being submitted in Search Console, and searches for your business name work almost immediately. Ranking for the services you offer takes longer, commonly several months for a new domain, which is why the launch date and the date you start getting enquiries from Google are not the same thing.
What should I have ready to make the project go faster?
The text for each page, your logo and brand colours, a handful of photographs, examples of websites you like, your domain login and a decision about who signs things off. Content is the single biggest cause of delay, so even rough drafts of the page text before the project starts will shorten the timescale more than anything else.